top of page
2 × 8″ HOT TAPS – CHILLER UNDERGROUND WATER LINE

Project Overview
WellFab completed two 8″ hot taps on a chiller underground water line, delivering precise new connections while maintaining full system operation.

Scope of Work
Two 8″ live hot taps on underground water line
• Installation of branch fittings and isolation valves
• Controlled cutting with secure coupon capture
• Pressure monitoring and integrity verification
• Clean tie-in and system restoration

Projects Impact
Careful planning and execution ensured safe operations within a confined
underground environment. The completed connections enhance system flexibility and support reliable long-term chiller performance.
bottom of page





